Project: Wastewater Collection System Rehabilitation and Renewal - File No. 4236-09

PM Construction & Rehab, LLC – ITB: D/M/WBE Certified Firms

 

Project: Wastewater Collection System Rehabilitation and Renewal - File No. 4236-09

Project Location: Houston, TX

Bid Due Date: 12/01/2022

Quotes Returned: 11/28/2022


Scopes:

 

Sanitary sewer cleaning & CCTV – 562998

  • Cleaning & CCTV Gravity Sewer
    • 6” – 36” Diameter Sewer
  • Siphon Cleaning & Inspection
    • 6” – 48” Diameter Siphon
  • Mechanical Cleaning
    • 6” – 36” Diameter Sewer

 

Traffic control - 561990

  • Flagmen & Certified Flagmen

 

Bypass Pumping for Sanitary Sewer - 237110

  • 6” – 16” setup and pump operation

 

Open Cut Utility Repairs (6” – 48” Diameter) - 238910

  • Hand Excavation Pits
  • Obstruction removal by excavation
  • Sanitary Sewer force Main replacement
  • Sanitary Sewer point repairs
  • Sanitary sewer main remove & Replacement
  • Slurry Boring
  • Air release valve removal & replacement on force main
  • Adjust Manholes
  • Air Release Valve Manhole Install
  • Standard FG manhole install
  • Precast concrete manhole install

 

Manhole Rehabilitation - 237110

  • Concrete Liner
    • COH Approved Products
  • Chemical Grout
  • Manhole Bench rehabilitation

 

Concrete & Asphalt repairs – 237310 / 238110

  • Remove & Replace concrete Driveway & Sidewalk
  • Curb & Gutter removal & Replacement
  • ADA Ramp Install
  • Asphalt Patching
  • Asphalt Mill & Overlay
  • Curb


Specs/Plans /Questions– Ashden Middlebrooks | amiddlebrooks@teamipr.com | 470-503-5624

Recent Posts

Inland Pipe Rehabilitation Announces Definitive Agreement to Acquire Inliner from Granite Construction Incorporated

Feb. 3, 2022  Inland Pipe Rehabilitation ("IPR"), a portfolio company of investment affiliates of J.F. Lehman & Company ("JFLCO"), announced...
Read more...

IPR awarded NASTT’s 2021 Outstanding Trenchless Paper Award for No-Dig Show

November 2021 Bill Sharpe, Business Development Manager of IPR Southeast, and Joe Royer, Vice President R&D of Geotree Solutions, were...
Read more...

CIPP Used on 54-In. Sewer Pipes in San Antonio

August 2010 San Antonio Texas Water System (SAWS) received a report of an enormous sinkhole developing on Benita Street, close...
Read more...

Inland Pipe Rehabilitation Installs Cured-In-Place Pipe Renewal System at Dallas Water Utility, Saving the City Significant Money and Avoiding Lengthy Shutdown

May 2013 Inland Pipe Rehabilitation (IPR), the nation’s largest privately-owned trenchless infrastructure solutions provider, recently installed Cured-In-Place Pipe (CIPP) to...
Read more...

slideup